Project Overview

Current Status

Project Name: Website Redesign for Client X

Project Manager: Alex Johnson

Start Date: January 10, 2025 ****

End Date (Expected): March 15, 2025

Current Phase/Stage: Development

Brief Description: Redesign the client’s e-commerce website for improved UX/UI and performance

Progress: On Track

Milestones Achieved: Wireframes approved, mockups finalized

Work Completed: Completed homepage and product page development

Pending Tasks: Integration of shopping cart and checkout pages

Percentage Completion: 65%

Issues and Risks

Next Steps

Current Issues: Delay in API documentation from the client

Risk Factors: Potential delay in the testing phase if APIs are not delivered by February 5, 2025

Mitigation Plans: Scheduled follow-up with the client on January 30, 2025

Dependencies: Delivery of API documentation from the client.

Immediate Actions: Begin integrating product pages with the backend

Next Milestones: Completion of shopping cart functionality by February 10, 2025

Resource Needs: Additional backend developer support

Communication/Meetings: Weekly check-in with stakeholders scheduled for February 2, 2025